Ofcom
Baldock
full design & build package
internal refurbishment
creation of new meeting rooms, hot desk areas and
open plan office area
M&E infrastructure
540m² of space
works completed in occupied building
project valued at £0.3m
8 week programme, phase one completed in
September 2009
further works include major car park alterations and
construction of breakout area
conservatory